Nyati Sacco Plaza 85% Done
No. | Works description | Status |
Casting of the 11th floor slab and beams | Completed | |
Masonry walling Partitions | Completed | |
Plaster work on internal walls | Completed | |
Skimming on stairwells | Done up to 7th floor | |
Floor screeding | 4th ,5th and 6th Floors done | |
Electrical works- conduits, power points | Conduits done up to 10th floor | |
Plumbing Works: Pipe work | Ongoing | |
Fire Fighting : Pipe work | Paused | |
Air conditioning Works | Ongoing |